On the 5th February we started. The digger came and the footings were duly excavated.
All the timber shuttering has been installed, and today they have finished building up the reinforcing bar structure that binds the root of the turbine tower into the concrete. Although ground conditions are not ideal, the rain has mostly kept off and we have had no hiccups.
Before bringing concrete to the site, we have to lay a temporary roadway of slatted steel on top of the ground, but we anticipate pouring the concrete next week. Five loads should do it.
All the timber shuttering has been installed, and today they have finished building up the reinforcing bar structure that binds the root of the turbine tower into the concrete. Although ground conditions are not ideal, the rain has mostly kept off and we have had no hiccups.
Before bringing concrete to the site, we have to lay a temporary roadway of slatted steel on top of the ground, but we anticipate pouring the concrete next week. Five loads should do it.